It cost a contractor $12,750 to manufacture their first unit. The company expects to experience a 94% unit learning curve. Estimate the cost of the 10th unit.
A $11,985
B $10,380
C $11,057
D $15,661
Purchase this Solution
Solution Summary
The solution describes the steps to estimate the cost of a given unit by using Learning Curve concepts.
Solution Preview
x=unit number=10
b=learning rate=94%
n=ln(b)/ln(2)=ln(94%)/ln(2)= ...
Education
- BEng (Hons) , Birla Institute of Technology and Science, India
- MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
- "Thank you"
- "Really great step by step solution"
- "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
- "Thanks Again! This is totally a great service!"
- "Thank you so much for your help!"
Purchase this Solution
Free BrainMass Quizzes
Cost Concepts: Analyzing Costs in Managerial Accounting
This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.
Income Streams
In our ever changing world, developing secondary income streams is becoming more important. This quiz provides a brief overview of income sources.
Balance Sheet
The Fundamental Classified Balance Sheet. What to know to make it easy.
Academic Reading and Writing: Critical Thinking
Importance of Critical Thinking
Motivation
This tests some key elements of major motivation theories.