Greendale stadium case:
Please show the network diagram and critical path for the #2
Show the gantt chart for #3
Calculate the EST, EFT, LST, LFT and do the slack analysis for all the activities.

Purchase this Solution

Solution Summary

The post illustrates how to draw the network diagram, calculate the critical path and draw the Gantt chart for a project and estimate the expected time of completion of the project.

Solution Preview

See the attached file. The text, tables and graphs may not print here properly.

Activity Number Activity Name Immediate Predecessor Normal Time
1 Baseball Stadium 0
2 Clear stadium Site 70
3 Demolish Building 2 30
4 Set up construction site 3 70
5 Drive support piling 2 120
6 Pour lower concrete bowl 5 120
7 Pour main concourse 3,6 120
8 Install playing field 3,6 90
9 Construct upper steel bowl 3,6 120
10 Install seats 7,9 140
11 Build luxury boxes 7,9 90
12 Install jumbotron 7,9 30
13 Stadium infrastructure 7,9 120
14 Construct steel canopy 10 75
15 Light installation 14 30
16 Build roof support 6 90
17 Construct roof 16 180
18 Install roof tracks 16 90
19 Install roof 17,18 90
20 Inspection 8,11,13,15,19 20

The network diagram is shown in following figure.

The EST, EFT, LST, LFT and slack ...

Purchase this Solution


Free BrainMass Quizzes
Lean your Process

This quiz will help you understand the basic concepts of Lean.

Basics of corporate finance

These questions will test you on your knowledge of finance.

Understanding the Accounting Equation

These 10 questions help a new student of accounting to understand the basic premise of accounting and how it is applied to the business world.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

MS Word 2010-Tricky Features

These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.