Yonan Inc. is considering Projects S and L

Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable.

In this particular case, if the decision is made by choosing the project with the shorter payback, some value (in terms of NPV) may be forgone. How much value will be lost in this instance?

WACC: 10.00%

0 1 2 3 4
CFS -$1,000 $500 $800 $0 $0
CFL -$2,100 $400 $800 $800 $1,000

Attachments

Solution Preview

Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable.

In this particular case, if the decision is made by choosing the project with the shorter payback, some value (in terms of NPV) may be ...

Solution Summary

This solution is comprised of a detailed explanation to determine how much value will be lost if Yonan choose one project over the other.

$2.19