Job sequencing problem

Not what you're looking for?

Ask Custom Question

The following jobs are waiting to be processed at your work center. The jobs are entered in the sequence in which they arrived.

Job Processing Time in Days Job Due Date in Days
A 4 7
B 2 4
C 8 11
D 3 5
E 5 11

In what sequence the jobs should be processed using the EDD scheduling rule?

a. Compute the average completion time for a job.
b. Compute the utilization rate.
c. Calculate the average number of jobs in the system.
d. Compute the average job lateness.

See attached file for full problem description.

Purchase this Solution

Solution Summary

This posting contains solution to following problem on sequencing. The expert examines operations management, sequencing jobs and the earliest due dates for jobs.

Purchase this Solution


Free BrainMass Quizzes
MS Word 2010-Tricky Features

These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.

Learning Lean

This quiz will help you understand the basic concepts of Lean.

Production and cost theory

Understanding production and cost phenomena will permit firms to make wise decisions concerning output volume.

Six Sigma for Process Improvement

A high level understanding of Six Sigma and what it is all about. This just gives you a glimpse of Six Sigma which entails more in-depth knowledge of processes and techniques.

Motivation

This tests some key elements of major motivation theories.