    Jobs @ Steves Machine Shop are sequenced using the slack per remaining operations rule. Determine the sequence of the following jobs waiting in queue

    Job Number 1 2 3 4 5 6

    Est. completion time (hrs) 15 10 8 6 10 7
    Due date (hrs) 25 19 20 17 28 15
    Remaining Ops 5 4 6 5 7 5