    SAMPLE OPERATIONS MANAGEMENT QUESTIONS WITH PRACTICAL PROBLEMS

    1. Average job completion time is:

    a. total processing time divided by the number of jobs.
    b. total flow time divided by the number of jobs
    c. total flow time divided by total processing time.
    d. total flow time minus total late time.

    2. Work center loading:

    a. is done prior to detailed scheduling.
    b. does not incorporate a priority sequence rule.
    c. is the assignment and commitment of specific jobs to each work center for the planning period.
    d. all of the above.

    3. When using the critical ratio ( CR ) priority sequence rule:

    a. a ratio of less than "1.0" implies that a job has a priority over a job with a ratio of more than "1.0".
    b. a ratio of more than "1.0" implies that a job has priority over a job with a ratio of less than "1.0".
    c. the job with the earliest 'due date' is scheduled first.
    d. none of the above.

    4. Which of the following is not a performance measure used in scheduling?

    a. job flow time.
    b. tardiness.
    c. labor capacity requirements.
    d. utilization.

    5. Gantt charts have several major limitations to include:

    a. the need to be updated regularly to account for new job arrivals and revised time estimates.
    b. the inability to assess the relative work loads at each work center.

    c. the inability to serve as a foundation for the detailed scheduling function.
    d. the inability to signal the need for reallocation of labor and equipment to busier work centers.

    6. Assume a task has the following times: a = 10, m = 25, and b = 40. Its ex-
    pected time is:

    a. 10
    b. 25
    c. 40
    d. 30
    e. none of the above.

    7. The critical path of a network is the:

    a. shortest time path through the network.
    b. path with the fewest activities.
    c. path with the most activities.
    d. longest time path through the network.
    e. none of the above.

    8. Given the following activity's optimistic, most likely, and pessimistic time es-
    timates of 2, 10, and 20 days respectively, compute the PERT variance for this activity:

    a. 3
    b. 6
    c. 9
    d. 18
    e. none of the above.

    -3-

    9. Managers use the network analysis of PERT and CPM to help them:

    a. derive flexibility by identifying noncritical activities.
    b. replan, reschedule, and reallocate resources such as manpower and finances.
    c. plan, schedule, monitor, and control large and complex projects.
    d. all of the above.

    10. In an activity-on-node (AON) network, the nodes represent______whereas
    the arcs represent _________.

    a. activities; time
    b. activities; precedence relationships
    c. events; activities
    d. precedence relationships; time

    True or False: ( select the one correct response )

    11. A job shop is a firm that specializes in medium- to large-volume production
    and utilizes line or continuous processes.

    TRUE FALSE

    12. The gantt chart ( for loading ) shows the order in which each job will be pro-
    cessed at each work center.

    TRUE FALSE

    13. Earliest due date ( EDD ) is a priority sequencing rule that states the job re-
    quiring the shortest processing time is the next job to be processed.

    TRUE FALSE

    14. Dispatching is the assignment and commitment of incoming jobs to one or
    more specific work centers, for the day or week.

    TRUE FALSE

    15. The DDATE priority sequence rule will always minimize average job late-
    ness.

    TRUE FALSE

    16. The gantt chart ( for loading ) provides the basis for the promised date of the
    job to the customer.

    TRUE FALSE

    17. The assignment algorithm is an alternative method for performing the load-
    ing function in a job shop.

    TRUE FALSE

    18. The gantt chart ( for supplementary scheduling ) allows management to
    monitor the progress of all jobs in the system in real time.

    TRUE FALSE

    19. Activities on the critical path exhibit positive slack times.

    TRUE FALSE

    20. The variance of project completion time equals the variances of all activities
    in the project.

    TRUE FALSE

    21. The expected activity time is the average of an activity's optimistic and pessi
    -mistic times.

    TRUE FALSE

    22. Dummy activities are found in activity-on-arc (AOA) convention PERT/
    CPM network models.

    TRUE FALSE

    23. The dummy activity has an expected time of zero by definition.

    TRUE FALSE

    24. Early start time ( ES ) is computed from right to left ( backward pass ).

    TRUE FALSE

    25. The project-group approach extends little or no formal authority to the
    project coordinator.

    TRUE FALSE

    PRACTICAL PROBLEMS

    26. In problem one, the static slack for job 'E' is:

    a. 3
    b. 4
    c. 5
    d. 6
    e. none of the above.

    27. In problem one, the static slack for job 'F' is:

    a. 16
    b. 15
    c. 14
    d. 13
    e. none of the above.

    28. In problem one, the lateness for job 'C' is:

    a. 0 days
    b. 1 day
    c. 2 days
    d. 5 days
    e. none of the above.

    29. In problem one, the average job completion time is:

    a. ≈ 12 days
    b. ≈ 13 days
    c. ≈ 14 days
    d. ≈ 15 days
    e. none of the above.

    -7-

    30. In problem one, the average job lateness is:

    a. 2.666 days
    b. 3.666 days
    c. 4.666 days
    d. 5.666 days
    e. none of the above.

    31. In problem one, the number of late jobs will be:

    a. 2
    b. 3
    c. 4
    d. 5
    e. none of the above.

    32. In problem two, the critical path is:

    a. 13 weeks
    b. 16 weeks
    c. 19 weeks
    d. 22 weeks
    e. none of the above.

    33. In problem two, the early finish ( EF ) time for activity 'H' is:

    a. 7th week
    b. 8th week
    c. 9th week
    d. 10th week
    e. none of the above.

    34. In problem two, the early start ( ES ) time for activity 'F' is:

    a. 5th week
    b. 6th week
    c. 7th week
    d. 8th week
    e. none of the above.
    -8-

    35. In problem two, the late start ( LS ) time for activity 'H' is:

    a. 16th week
    b. 17th week
    c. 18th week
    d. 19th week
    e. none of the above.

    36. In problem two, the late finish ( LF ) time for activity 'F' is:

    a. 16th week
    b. 17th week
    c. 18th week
    d. 19th week
    e. none of the above.

    37. In problem two, the slack time ( S ) for activity 'D' is:

    a. 0 weeks
    b. 1 week
    c. 2 weeks
    d. 3 weeks
    e. 4 weeks

    38. In problem three, car '3' will be assigned to:

    a. Bob
    b. Fred
    c. Mike
    d. Tim

    39. In problem three, car '1' will be assigned to:

    a. Bob
    b. Fred
    c. Mike
    d. Tim

    -9-

    40. In problem three, the total number of labor hours required will be:

    a. 30 hours
    b. 35 hours
    c. 40 hours
    d. 45 hours
    e. none of the above.

    © BrainMass Inc. brainmass.com October 10, 2019, 7:03 am ad1c9bdddf
    https://brainmass.com/business/business-management/566540

    Solution Preview

    See the attached files. Thanks

    SAMPLE OPERATIONS MANAGEMENT QUESTIONS WITH PRACTICAL PROBLEMS

    1. Average job completion time is:

    a. total processing time divided by the number of jobs.
    b. total flow time divided by the number of jobs
    c. total flow time divided by total processing time.
    d. total flow time minus total late time.

    Answer: b. total flow time divided by the number of jobs

    2. Work center loading:

    a. is done prior to detailed scheduling.
    b. does not incorporate a priority sequence rule.
    c. is the assignment and commitment of specific jobs to each work center for the planning period.
    d. all of the above.

    Answer d. All of the above

    3. When using the critical ratio ( CR ) priority sequence rule:

    a. a ratio of less than "1.0" implies that a job has a priority over a job with a ratio of more than "1.0".
    b. a ratio of more than "1.0" implies that a job has priority over a job with a ratio of less than "1.0".
    c. the job with the earliest 'due date' is scheduled first.
    d. none of the above.

    Answer: a. a ratio of less than "1.0" implies that a job has a priority over a job with a ratio of more than "1.0".

    4. Which of the following is not a performance measure used in scheduling?

    a. job flow time.
    b. tardiness.
    c. labor capacity requirements.
    d. utilization.

    Answer: c. labor capacity requirement

    5. Gantt charts have several major limitations to include:

    a. the need to be updated regularly to account for new job arrivals and revised time estimates.
    b. the inability to assess the relative work loads at each work center.
    c. the inability to serve as a foundation for the detailed scheduling function.
    d. the inability to signal the need for reallocation of labor and equipment to busier work centers.

    Answer: a. the need to be updated regularly to account for new job arrivals and revised time estimates.
    .

    6. Assume a task has the following times: a = 10, m = 25, and b = 40. Its ex-
    pected time is:

    a. 10
    b. 25
    c. 40
    d. 30
    e. none of the above.
    Expected time = (10+25*4+40)/6=25
    Answer b. 25

    7. The critical path of a network is the:

    a. shortest time path through the network.
    b. path with the fewest activities.
    c. path with the most activities.
    d. longest time path through the network.
    e. none of the above.

    Answer d. longest time path through the network.

    8. Given the following activity's ...

    Solution Summary

    This post is a practice test for the production management exam. 40 questions. Has word as well as excel file.