Consider a project having the following ten activities. What is the slack time of activity B?
Activity A B C D E F G H I J
Immediate
Predecessor None None A A, B C, D D C E, G E, F H, I
Time (weeks) 7 3 5 6 4 4 9 8 6 5.

Purchase this Solution

Solution Summary

Solution determines the slack time for given activity.

Solution provided by:
Education
  • BEng (Hons) , Birla Institute of Technology and Science, India
  • MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
  • "Thank you"
  • "Really great step by step solution"
  • "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
  • "Thanks Again! This is totally a great service!"
  • "Thank you so much for your help!"
Purchase this Solution


Free BrainMass Quizzes
Motivation

This tests some key elements of major motivation theories.

Basic Social Media Concepts

The quiz will test your knowledge on basic social media concepts.

Basics of corporate finance

These questions will test you on your knowledge of finance.

Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce

Team Development Strategies

This quiz will assess your knowledge of team-building processes, learning styles, and leadership methods. Team development is essential to creating and maintaining high performing teams.