2) Cosider the network pictured below with task durations in days as follows:
A=2, B= 6, C=5, D=2, E=6, and F=1

a) Enumerate all paths and their duration through this network
b) Calculate the critical path for the network
c) What is the minimum duration of the project?
d) How much slack exists at each activity

A----------C----------E
Start End
B-----------D----------F

© BrainMass Inc. brainmass.com October 17, 2018, 4:23 am ad1c9bdddf
https://brainmass.com/business/accounting/calculating-critical-paths-slack-time-459905

Solution Summary

The solution calculates the critical paths and slack time. A five-page detailed solution showing the step-by-step guide in arriving to a solution is attached.

$2.19
Similar Posting

Project Management:(CPM Problem) Calculate EFT,LFT, Slack, Critical path

Use Excel to solve the following:

Given the following network with activity times in months, determine the earliest and latest activity times and slack for each activity. Indicate the critical path and the project duration.

(see diagram in the attached file)