    Two workers have the same job assembling units for shipment to customers. The first worker can assemble 100 units in 3 hours. The second worker can assemble 85 units in 2 hours. Which worker is more productive?

    Worker Input Output Productivity
    1 3 100 33.33333333
    2 2 85 42.5

    In the above problem we have gathered more data:

    Profit per unit sold (Sales Price - (Cost of Sales))= $75

    Worker 1 produces 1 defect per hour worked. Worker 2 produces 3 defects per hour worked.
    Which worker is more productive in terms of delivering profit to the company?

    Worker Input Shippable Output Productivity Profit per Hour Worked
    1 3
    2 2

    © BrainMass Inc. brainmass.com June 4, 2020, 3:06 am ad1c9bdddf
    https://brainmass.com/business/business-management/calculating-productivity-assembly-units-498621

    Attachments

    Solution Preview

    Hi

    Please find attached the response to your question.

    Hope it is useful.

    Two workers have the same job assembling units for shipment to customers. The first worker can assemble 100 units in 3 hours. The second worker can assemble 85 ...

    Solution Summary

    The expert calculates the productivity of assembly units. The productivity in terms of delivering profit to the company is determined.

    $2.19

    ADVERTISEMENT