Two workers have the same job assembling units for shipment to customers. The first worker can assemble 100 units in 3 hours. The second worker can assemble 85 units in 2 hours. Which worker is more productive?

Worker Input Output Productivity
1 3 100 33.33333333
2 2 85 42.5

In the above problem we have gathered more data:

Profit per unit sold (Sales Price - (Cost of Sales))= $75

Worker 1 produces 1 defect per hour worked. Worker 2 produces 3 defects per hour worked.
Which worker is more productive in terms of delivering profit to the company?

Worker Input Shippable Output Productivity Profit per Hour Worked
1 3
2 2

© BrainMass Inc. brainmass.com October 25, 2018, 7:17 am ad1c9bdddf
https://brainmass.com/business/business-management/calculating-productivity-assembly-units-498621

Attachments

Solution Preview

Hi

Please find attached the response to your question.

Hope it is useful.

Two workers have the same job assembling units for shipment to customers. The first worker can assemble 100 units in 3 hours. The second worker can assemble 85 ...

Solution Summary

The expert calculates the productivity of assembly units. The productivity in terms of delivering profit to the company is determined.

$2.19
See Also This Related BrainMass Solution

Calculating productivity: Netty's Christmas Trees

Netty produces Christmas tree ornaments for resale at local craft fairs and Christmas bazaars. She is currently working a total of 15 hours per day to produce 300 ornaments.
a) What is Netty's productivity?
b) Netty thinks that by redesigning the ornaments and switching from contact cement to a hot-glue gun, she can increase her total production to 400 ornaments per day. What would be her new productivity?
c) What would be the increase in productivity?

View Full Posting Details