Bowman Builders manufactures steel storage sheds for commercial use. Joe Bowman, president of Bowman Builders, is contemplating producing sheds for home use. The activities necessary to build an experimental model and related data are given in the accompanying table.
(a) What is the project completion date?
(Formulate an LP problem to crash this project to 10 weeks.

ACTIVITY NORMAL CRASH NORMAL CRASH IMMEDIATE
TIME TIME COST COST PREDECESSORS

A 3 2 1,000 1,600 --------------
B 2 1 2,000 2,700 -------------
C 1 1 300 300 ------------
D 7 3 1,300 1,600 A
E 6 3 850 1,000 B
F 2 1 4,000 5,000 C
G 4 2 1,500 2,000 D, E

Purchase this Solution

Solution Summary

This solution provides assistance with the project management problem for Bowman Builders.

Purchase this Solution


Free BrainMass Quizzes
Measures of Central Tendency

Tests knowledge of the three main measures of central tendency, including some simple calculation questions.

Terms and Definitions for Statistics

This quiz covers basic terms and definitions of statistics.

Know Your Statistical Concepts

Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.

Measures of Central Tendency

This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.