Purchase Solution

Activity Estimation Constructions

Not what you're looking for?

Ask Custom Question

Suppose the following estimates of activities (in weeks) for the construction of a swimming pool were provided, along with their immediate predecessors. What is the probability that the project will be completed within 21 weeks? Within 22 weeks?
Activity A B C D E F G H
Immediate Predecessor - - A A B D, E D, E C, F

Activity Optimistic Most Probable Pessimistic
A 4.0 5.0 6.0
B 2.5 3.0 3.5
C 6.0 7.0 8.0
D 5.0 5.5 9.0
E 5.0 7.0 9.0
F 2.0 3.0 4.0
G 8.0 10.0 12.0
H 6.0 7.0 14.0

Attachments
Purchase this Solution

Solution Summary

The expert examines activity estimation constructions.

Solution Preview

Please see the attached file. Thanks
Problem E4-6
Suppose the following estimates of activities (in weeks) for the construction of a swimming pool were provided, along with their immediate predecessors. What is the probability that the project will be completed within 21 weeks? Within 22 weeks?
Activity A B C D E F G H
Immediate Predecessor - - A A B D, E D, E C, F

Activity Optimistic Most Probable Pessimistic
A 4.0 ...

Purchase this Solution


Free BrainMass Quizzes
Measures of Central Tendency

This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.

Measures of Central Tendency

Tests knowledge of the three main measures of central tendency, including some simple calculation questions.

Know Your Statistical Concepts

Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.

Terms and Definitions for Statistics

This quiz covers basic terms and definitions of statistics.