Wheeler Corporation constructed a building at a cost of $20,000,000. Average accumulated expenditures were $8,000,000, actual interest was $1,200,000, and avoidable interest was $600,000. If the salvage value is $1,600,000, and the useful life is 40 years, depreciation expense for the first full year using the straight-line method is

Sweet Knee Company is constructing a building. Construction began in 2008 and the building was completed 12/31/08. Sweet Knee made payments to the construction company of $1,000,000 on 7/1, $2,100,000 on 9/1, and $2,000,000 on 12/31. Average accumulated expenditures were

Purchase this Solution

Solution Summary

The solution explains how to calculate the average accumulated expenditures and the total cost of the building.

Solution Preview

1. In case of construction of a building, the avoidable interest is capitalized. The cost of the building will be 20,000,000+600,000=20,600,000. ...

Purchase this Solution


Free BrainMass Quizzes
Organizational Leadership Quiz

This quiz prepares a person to do well when it comes to studying organizational leadership in their studies.

Employee Orientation

Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.

Organizational Behavior (OB)

The organizational behavior (OB) quiz will help you better understand organizational behavior through the lens of managers including workforce diversity.

Social Media: Pinterest

This quiz introduces basic concepts of Pinterest social media

Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.