Explore BrainMass

Explore BrainMass

    Project Variances-earned Value Analysis

    Not what you're looking for? Search our solutions OR ask your own Custom question.

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI?

    © BrainMass Inc. brainmass.com March 4, 2021, 7:32 pm ad1c9bdddf
    https://brainmass.com/business/project-management/project-variances-earned-value-analysis-107526

    Solution Preview

    A project in its 26th week has an actual cost of $270,000.  It was scheduled to have spent $261,000.  For the work performed to date, the budgeted value is $272,000.  What are the cost and schedule variances for the project?  What are the SPI and CPI?

    BCWS - Budgeted Cost of Work Scheduled = $261,000
    ACWP - Actual Cost of Work Performed = $270,000
    BCWP - Budgeted Cost of Work Performed ...

    Solution Summary

    The solution calculates Spending variance, Schedule variance, Schedule Performance Index (SPI) , Cost Performance Index (CPI) given BCWS (Budgeted Cost of Work Scheduled), ACWP (Actual Cost of Work Performed) and BCWP (Budgeted Cost of Work Performed).

    $2.49

    ADVERTISEMENT