Project Variances-earned Value Analysis

A project has just completed the 87th item in its action plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?

Solution Preview

"A project has just completed the 87th item in its action plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?
"

BCWS - Budgeted Cost of Work Scheduled = $168,000
ACWP - Actual Cost of Work Performed ...

Solution Summary

The solution calculates Spending variance, Schedule variance, Schedule Performance Index (SPI) , Cost Performance Index (CPI) given BCWS (Budgeted Cost of Work Scheduled), ACWP (Actual Cost of Work Performed) and BCWP (Budgeted Cost of Work Performed).

$2.19