Explore BrainMass
Share

Project Variances-earned Value Analysis

This content was STOLEN from BrainMass.com - View the original, and get the already-completed solution here!

A project has just completed the 87th item in its action plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?

© BrainMass Inc. brainmass.com October 24, 2018, 8:47 pm ad1c9bdddf
https://brainmass.com/business/project-management/107890

Solution Preview

"A project has just completed the 87th item in its action plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?
"

BCWS - Budgeted Cost of Work Scheduled = $168,000
ACWP - Actual Cost of Work Performed ...

Solution Summary

The solution calculates Spending variance, Schedule variance, Schedule Performance Index (SPI) , Cost Performance Index (CPI) given BCWS (Budgeted Cost of Work Scheduled), ACWP (Actual Cost of Work Performed) and BCWP (Budgeted Cost of Work Performed).

$2.19
See Also This Related BrainMass Solution

Word Problem

A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI?

View Full Posting Details