Project Variances-earned Value Analysis

A project has just completed the 87th item in its action plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?

© BrainMass Inc. brainmass.com August 15, 2018, 12:55 am ad1c9bdddf

Solution Preview

"A project has just completed the 87th item in its action plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?
"

BCWS - Budgeted Cost of Work Scheduled = $168,000
ACWP - Actual Cost of Work Performed ...

Solution Summary

The solution calculates Spending variance, Schedule variance, Schedule Performance Index (SPI) , Cost Performance Index (CPI) given BCWS (Budgeted Cost of Work Scheduled), ACWP (Actual Cost of Work Performed) and BCWP (Budgeted Cost of Work Performed).