    The project management chart that graphically models the sequence of project tasks and their interrelationships using a flowchart diagrams is called a:

    a. Gantt Chart.
    b. PERT chart.
    c. flow diagram.
    d. SOW chart.

    © BrainMass Inc. brainmass.com March 4, 2021, 9:12 pm ad1c9bdddf
    https://brainmass.com/business/project-management/pert-chart-224941

    Solution Summary

    Solution matches the given defintion with a correct project management chart.