Operations management - Process analysis in project management

Not what you're looking for?

Ask Custom Question

See attached file for full question.

1. List all paths & their normal durations in the columns of the table below; following the example...

2. How many weeks do you expect the project to take (without unexpected delays or crashing?)

3. How many weeks after its early start time could the start of activity C be delayed without delaying project completion?

4. What is the minimum # of weeks in which the project could be completed (by crashing)?

5. Suppose that the project manager must pay a penalty of $3000 for each week of project duration past 16. What project duration minimizes penalty + crash costs?

Purchase this Solution

Solution Summary

The solution completes the information including a PERT chart, and detailed explanations.

Purchase this Solution


Free BrainMass Quizzes
Writing Business Plans

This quiz will test your understanding of how to write good business plans, the usual components of a good plan, purposes, terms, and writing style tips.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

Paradigms and Frameworks of Management Research

This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.

Academic Reading and Writing: Critical Thinking

Importance of Critical Thinking

Learning Lean

This quiz will help you understand the basic concepts of Lean.