Develop a Work Breakdown Structure (WBS) and project schedule in a Gantt format for an E-Mail Upgrade Project. The WBS and resultant schedule should contain the following high-level activities:

1.0 Evaluate User & System Requirements
2.0 Evaluate ODHS Network Suitability
3.0 Conduct E-mail System Selection
4.0 Upgrade Ohio Department of Human Service Network & Hardware
5.0 Develop E-mail Training
6.0 Deploy E-mail System

Each of the six WBS elements should be decomposed into two or more activities; additionally, three of these six elements should be decomposed into a third level consisting of at least two more activities. Thus, there should be six high level WBS elements, twelve or more second level activities (two per the six elements), and six third level activities. Use the format described above to define the activities (action verb followed by subject, such as Deploy E-mail System).

The Gantt chart should be developed based on the WBS (all activities should be detailed on the Gantt chart). The Gantt chart should reflect the proper dependencies of each of the activities (for example, you can't have "Deploy E-mail System" before "Evaluate User Requirements"). For activity duration, provide a reasonable estimate of the time you expect each activity to take; while students are not expected to provide accurate durations, durations should be reasonably defensible and logical. For formatting ease, high level activities should be left justified while second and third level activities should be indented below their parent activities.

Purchase this Solution

Purchase this Solution


Free BrainMass Quizzes
Production and cost theory

Understanding production and cost phenomena will permit firms to make wise decisions concerning output volume.

MS Word 2010-Tricky Features

These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.

Business Ethics Awareness Strategy

This quiz is designed to assess your current ability for determining the characteristics of ethical behavior. It is essential that leaders, managers, and employees are able to distinguish between positive and negative ethical behavior. The quicker you assess a person's ethical tendency, the awareness empowers you to develop a strategy on how to interact with them.

Business Processes

This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.

Paradigms and Frameworks of Management Research

This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.