Changes to total fixed costs due to production level changes

At a production level of 5,600 units a project has total costs of $89,000. The variable cost per unit is $11.20. What is the amount of the total fixed costs if the production level is increased to 6,100 units without increasing the total fixed assets?

Solution Preview

Fixed costs = Total costs - unit variable cost * quantity = ...

Solution Summary

This is a solution calculating the amount of the total fixed costs if the production level is increased without the total fixed assets increasing.