A project budget report is showing our project as spending 35,000 against a budgeted amount of 40,000. What does this report tell you about the project?
1. we can't be sure how the project is going
2. we should check to see if all bills have been paid
3. we are doing a good job managing the project
4. we are spending less than we should for the project
Purchase this Solution
Solution Summary
The solution is concise and to the point and explains the concepts very well. The solution is very easy to understand as well. Overall, an excellent response to the question being asked.
Solution Preview
The correct answer is 1. Spending less than the budgeted amount does not mean that we are doing good. We ...
Purchase this Solution
Free BrainMass Quizzes
Balance Sheet
The Fundamental Classified Balance Sheet. What to know to make it easy.
Academic Reading and Writing: Critical Thinking
Importance of Critical Thinking
IPOs
This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)
Six Sigma for Process Improvement
A high level understanding of Six Sigma and what it is all about. This just gives you a glimpse of Six Sigma which entails more in-depth knowledge of processes and techniques.
Basics of corporate finance
These questions will test you on your knowledge of finance.