Explore BrainMass
Share

Explore BrainMass

    Implementing the Activity Based Costing (ABC) System

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    See the attached file.
    Jarme Company makes two products and is implementing an Activity Based Costing (ABC) system. Previously, all overhead had been applied on the basis of machine hours. The Company produces 100,000 units of product D and 5,000 units of product F.
    Cost Pool Driver and Level Cost in Pool Use of Driver by Product D Use of Driver by Product F
    Equipment Setup 500 setups $1,000,000 350 setups 150 setups
    Materials Ordering 10,000 orders $2,000,000 7,000 orders 3,000 orders
    Quality Control 4,000 inspections $500,000 2,000 inspections 2,000 inspections
    Machining 50,000 machine hours $5,000,000 40,000 machine hours 10,000 machine hours

    1. What is the overhead cost per unit for Product D when all overhead is applied based on machine hours?
    A. $170
    B. $68
    C. $340
    D. $40

    2. What is the overhead cost per unit for Product F using ABC?
    A. $63.50
    B. $430
    C. $68
    D. $340

    3. Which two cost pools could be combined without affecting the unit costs using ABC?
    A. Equipment setup and Machining
    B. Materials ordering and Quality Control
    C. Materials ordering and Machining
    D. Equipment setup and Materials Ordering

    4. Using ABC, what is the cost per setup in the Equipment Setup pool?
    A. $700,000
    B. $2,000
    C. $9.52
    D. $100

    5. What is the overhead cost per unit for Product F when all overhead is applied based on machine hours?
    A. $170
    B. $340
    C. $68
    D. $200

    6. What is the overhead cost per unit for Product D using ABC?
    A. $63.50
    B. $430
    C. $68
    D. $340

    7. . Using ABC, what is the cost per machine hour in the Machining pool?
    A. $100
    B. $4,000,000
    C. $47.62
    D. $2,000.

    © BrainMass Inc. brainmass.com October 10, 2019, 2:05 am ad1c9bdddf
    https://brainmass.com/business/product-costing/implementing-activity-based-costing-abc-system-362022

    Attachments

    Solution Summary

    The solution discusses implementing the activity based costing system.

    $2.19