    Consider the bill of material for Product J and the data given in the following table. The gross requirements for J are 200 units in week 6 and 250 units in week 8. Develop the MRP tables for each item for an 8 week planning period. Use the lot-for-lot lot-sizing rule.

    J is dependent on K(1) which is dependent on L(4)
    J is dependent of M(2)

    Item - Lead time - Quantity on Hand - Scheduled receipts

    J 1 0

    K 2 20 30 in week 2

    L 2 0

    M 1 20 10 in week 1

    What is the planned orders for J in period 5?
    What is the gross requirements for J in period 8?
    What are the planned orders for K in period 2?
    What are the planned receipts for K i period 7?
    What are the planned order for L in period 1?

    © BrainMass Inc. brainmass.com October 9, 2019, 10:15 pm ad1c9bdddf
    https://brainmass.com/business/organizational-structure/mrp-structure-213666

    Solution Summary

    Word file shows calculations of the planned orders , the gross requirements and the planned receipts for various product.