Cost of equipment 50,000
working capital required 30,000
salvage value 0
annual cash inflows 20,000
required rate of return 20%
life of project 8 years

NPV=

A 3730
B 0
C 32,450
D 88,370

Solution Preview

cost of equipment 50,000
working capital required 30,000
salvage value ...

Solution Summary

NPV computed in excel for you.