Purchase Solution

Scott Contract to Park Industries & Follow on Contract

Not what you're looking for?

Ask Custom Question

The Bathtub Period

The award of the Scott contract on January 3, 1987, left Park Industries elated. The Scott Project, if managed correctly, offered tremendous opportunities for follow-on work over the next several years. Park's management considered the Scott Project as strategic in nature.

The Scott Project was a ten-month endeavor to develop a new product for Scott Corporation. Scott informed Park Industries that sole-source production contracts would follow, for at least five years, assuming that the initial R&D effort proved satisfactory. All follow-on contracts were to be negotiated on a year-to-year basis.

Jerry Dunlap was selected as project manager. Although he was young and eager, he understood the importance of the effort for future growth of the company. Dunlap was given some of the best employees to fill out his project office as part of Park's matrix organization. The Scott Project maintained a project office of seven full-time people, including Dunlap, throughout the duration of the project. In addition, eight people from the functional department were selected for representation as functional project team members, four full-time and four half-time.

Although the workload fluctuated, the manpower level for the project office and team members was constant for the duration of the project at 2,080 hours per month. The company assumed that each hour worked incurred a cost of $60.00 per person, fully burdened.

At the end of June, with four months remaining on the project, Scott Corporation informed Park Industries that, owing to a projected cash flow problem, follow-on work would not be awarded until the first week in March (1988). This posed a tremendous problem for Jerry Dunlap because he did not wish to break up the project office. If he permitted his key people to be assigned to other projects, there would be no guarantee that he could get them back at the beginning of the follow-on work. Good project office personnel are always in demand.

Jerry estimated that he needed $40,000 per month during the â??bathtubâ?? period to support and maintain his key people. Fortunately, the bathtub period fell over Christmas and New Year's, a time when the plant would be shut down for seventeen days. Between the vacation days that his key employees would be taking, and the small special projects that his people could be temporarily assigned to on other programs, Jerry revised his estimate to $125,000 for the entire bathtub period.

At the weekly team meeting, Jerry told the program team members that they would have to â??tighten their beltsâ?? in order to establish a management reserve of $125,000. The project team understood the necessity for this action and began rescheduling and replanning until a management reserve of this size could be realized. Because the contract was firm-fixed-price, all schedules for administrative support (i.e., project office and project team members) were extended through February 28 on the supposition that this additional time was needed for final cost data accountability and program report documentation.

Jerry informed his boss, Frank Howard, the division head for project management, as to the problems with the bathtub period. Frank was the intermediary between Jerry and the general manager. Frank agreed with Jerry's approach to the problem and requested to be kept informed.

On September 15, Frank told Jerry that he wanted to â??bookâ?? the management reserve of $125,000 as excess profit since it would influence his (Frank's) Christmas bonus. Frank and Jerry argued for a while, with Frank constantly saying, â??Don't worry! You'll get your key people back. I'll see to that. But I want those uncommitted funds recorded as profit and the program closed out by November 1.â??

Jerry was furious with Frank's lack of interest in maintaining the current organizational membership.

a.Should Jerry go to the general manager?

b.Should the key people be supported on overhead?

c.If this were a cost-plus program, would you consider approaching the customer with your problem in hopes of relief?

d.If you were the customer of this cost-plus program, what would your response be for additional funds for the bathtub period, assuming cost overrun?

e.Would your previous answer change if the program had the money available as a result of an underrun?

f.How do you prevent this situation from recurring on all yearly follow-on contracts?

Purchase this Solution

Solution Summary

This solution deals with a case study involving the awarding of the Scott contract to Park Industries, and a situation called "The Bathtub Period" It answers questions involving follow on contracts, talking to management about a supervisor's actions, cost plus programs, supporting key people on overhead, and under runs. It is thorough and supported with examples.

Solution Preview

a. Jerry should go to the general manager. It is an uncomfortable situation, however, Frank intends to cheat the company. If Jerry neglects to alert the chain of command, Jerry will be complicit in the fraud. It is wrong to lie, even when a bonus is tied to the lie. Plus, how much weight can Frank's words carry, that Jerry will get his key people back, if he is willing to lie about the reserve? At what point can Jerry or the company trust Frank? Jerry must speak with the general manager.

b. Unfortunately, the key people should not be supported on the overhead, unless this sum of money is an affordable sum to the company. It is not reasonable for Scott Corporation to expect Jerry and his management team to stand in place ...

Solution provided by:
Education
  • BA, University of Southern California
  • MSS, United States Sports Academy
  • Ed.D, Boise State University
Recent Feedback
  • "Thk u"
  • "Thank you!:)"
  • "Thank you!:)"
  • "Thank you!:)"
  • "Thank you!:)"
Purchase this Solution


Free BrainMass Quizzes
Team Development Strategies

This quiz will assess your knowledge of team-building processes, learning styles, and leadership methods. Team development is essential to creating and maintaining high performing teams.

Organizational Behavior (OB)

The organizational behavior (OB) quiz will help you better understand organizational behavior through the lens of managers including workforce diversity.

IPOs

This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)

Organizational Leadership Quiz

This quiz prepares a person to do well when it comes to studying organizational leadership in their studies.

Social Media: Pinterest

This quiz introduces basic concepts of Pinterest social media