Exercise 10- 9 Material and Labor Variances [LO2, LO3]
Topper Toys has developed a new toy called the Brainbuster. The company has a standard cost system to help control costs and has established the following standards for the Brainbuster toy:
Direct materials: 8 diodes per toy at $0.30 per diode
Direct labor: 1.2 hours per toy at $7 per hour
During August, the company produced 5,000 Brainbuster toys. Production data on the toy for August follow:
Direct materials: 70,000 diodes were purchased at a cost of $0.28 per diode. 20,000 of these diodes were still in inventory at the end of the month. Direct labor: 6,400 direct labor-hours were worked at a cost of $48,000.
Requirement 1:
Compute direct materials price and quantity variances for August. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance)). Input all amounts as positive values. Omit the "$" sign in your response.
Material price variance $
Material quantity variance $
________________________________________
Requirement 2:
Compute direct labor rate and efficiency variances for August. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance)). Input all amounts as positive values. Omit the "$" sign in your response.
Direct material/labor variances Compute the following variances indicating whether each variance is favorable or unfavorable- a. Direct-material price variance...
...Variances Star Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat is as follows: Materials ( ...
... Production reported that 725 direct labor-hours were ...materials: a.) Compute the direct materials price and ...Material Price Variance = (AP-SP) AQ Actual Price AP ...
Material and Labor Variances Consider the following data: Costs incurred: actual inputs × actual prices incurred Direct Materials $154,000 Direct Labor...
... the direct materials variance, including its price and quantity variances. 2. Compute the direct labor variance, including its rate and efficiency variances. ...
... the company purchased 6,000 pounds of direct materials at a ... All of this material was used in the production of ... Direct labor cost totaled $28,500 for the month. ...
... Cost per pound 2.5 Total direct material cost 58,500 ... per hour 15 Total direct labor cost 585,000 ... 2. Variance calculation Direct Materials Price Variance = AQ(AP ...
Direct Labor Variance, Material Quantity, etc. Arrow Industries employs a standard cost system in which direct materials inventory is carried at standard cost. ...