Share
Explore BrainMass

Materials Requirement Planning

2. One unit of A is made of two units of B, three units of C, and two units of D. B is composed of one unit of E and two units of F. C is made of two units of F and on unit of D. E is made of two units of D. Items, A, C, D, and F have one-week lead times; B and E have lead times of two weeks. Lot-for-lot (L4L) lot sizing is used for Items A, B, C, and D; lots of size 50 and 180 are used for Items E and F, respectively. Item C has an on-hand (beginning) inventory of 15; D has an-on hand inventory of 50; all other items have zero beginning inventory. We are schedule to receive 20 units of Item E in Week 2; there are no other schedule receipts. Construct the bill of materials and indented parts list. If 20 units of A are required in Week 8, find the necessary planned order release for all components.

Attachments

Solution Summary

Solutions describes the necessary planned order release for all components.

$2.19