    Operations Management-Oakwood Outpatient Clinic

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Oakwood Outpatient Clinic is analyzing its operation in an effort to improve performance. The clinic estimates that a patient spends on average 3.5 hours at the facility. The amount of time the patient is in contact with staff (i.e., physicians, nurses, office staff, lab technicians) is estimated at 40 minutes. On average the facility sees 42 patients per day. Their standard has been 40 patients per day. Determine process velocity and efficiency for the clinic.

    © BrainMass Inc. brainmass.com June 4, 2020, 2:57 am ad1c9bdddf
    https://brainmass.com/business/business-management/operations-management-oakwood-outpatient-clinic-490434

    Solution Summary

    This solution provides steps to determine velocity and efficiency.