Business Management: End Date Impacts on Projects

The attachment has a network, with all times indicating weeks, answer the following questions:
a. What is the impact on the end date of the project if activity B slips by two weeks?
b. What is the impact on the end date of the project if activity E slips by one week?
c. What is the impact on the end date of the project if activity D slips by two weeks?
d. If the customer offered you a bonus for completing the project in sixteen weeks or less, which activities would you focus on first as part of compression ("crashing") analyses?

Attachments

Solution Preview

//Please note I have only attached the basic information for the impact. You will need to expand on these and understand the concepts better from your text. This is simply a guide to help you complete this paper.//

End Date Impacts on Projects- Business Management
The attachment has a network, with all times indicating weeks, answer the following questions:

a. What is the impact on the end date of the project if activity B slips by two weeks?
There will be ...

Solution Summary

The end dates impact on projects in business management are determined.