    Kanban Cards Needed for Safety Stock

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    A bottling plant fills 2,400 bottles every two hours. The lead time is 40 minutes and a container accommodates 120 bottles. The safety stock is 10 percent of expected demand. How many kanban cards are needed?

    © BrainMass Inc. brainmass.com June 3, 2020, 9:01 pm ad1c9bdddf
    https://brainmass.com/business/business-management/a-bottling-plant-fills-2-400-bottles-every-two-hours-162931

    Solution Summary

    Brief calculations show how to find the number of kanban cards a bottling plant needs.