Explore BrainMass

Explore BrainMass

    Calculating the number of kanban containers

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    The Jewel Golf Club Company, which recently began using a Kanban system, has had problems with high inventory levels of one of the handle grips used to make several versions of its clubs. Daily demand for the grip is 3000 units, average waiting time during production is 0.20 day, processing time is 0.10 day per container, and a container holds 150 grips.How many Kanban containers would Jewel require if a 15% policy variable is used?

    © BrainMass Inc. brainmass.com June 4, 2020, 4:30 am ad1c9bdddf
    https://brainmass.com/business/business-management/564160

    Solution Summary

    Solution depicts the steps to estimate the number of kanban containers in the given case.

    $2.19

    ADVERTISEMENT