Purchase Solution

Calculating Land and Building Cost

Not what you're looking for?

Ask Custom Question

1. On February 10, 2013, Rims Corporation purchased a parcel of land as a factory site for $250,000. An old building on the property was demolished, and construction began on a new building which was completed on September 30, 2013. Salvaged materials resulting from the demolition were sold for $10,000. Costs incurred during this period included: Demolition of old building.... $40,000, Architect's fees.... $20,000, Legal fees for title investigation and purchase contract.... $6,000, and Construction costs.... $750,000. Rims should record the cost of the land and new building, respectively, as

a. $286,000 and $770,000
b. $286,000 and $750,000
c. $250,000 and $770,000
d. $250,000 and $750,000

Purchase this Solution

Solution Summary

This solution shows how Rims should record the cost of land and the new building, according to GAAP.

Purchase this Solution


Free BrainMass Quizzes
IPOs

This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)

Learning Lean

This quiz will help you understand the basic concepts of Lean.

Organizational Leadership Quiz

This quiz prepares a person to do well when it comes to studying organizational leadership in their studies.

Change and Resistance within Organizations

This quiz intended to help students understand change and resistance in organizations

Marketing Management Philosophies Quiz

A test on how well a student understands the basic assumptions of marketers on buyers that will form a basis of their marketing strategies.