Case 12-4: Component Technologies, Inc.: Adding FlexConnex Capacity

In 2002, Component Technologies, Inc. (CTI) manufactured components, such as interconnect components, electronic connectors, fiber-optic connectors, flexible interconnects, coaxial cable, cable assemblies, and interconnect systems, used in computers and other electronic equipment. CTI's global marketing strategy produced significant growth; CTI was now one of three major suppliers in its market segments. Major customers included other global companies, such as IBM, HP, Hitachi, and Siemens. These companies, in turn, manufactured and marketed their products worldwide.

FlexConnex, one of CTI's largest selling products, was very profitable (see Exhibit 1). The Santa Clara, California plant that manufactured the FlexConnex component was projected to reach its full capacity of 75 million units in 2003. With sufficient capacity to meet demand, CTI expected its sales of FlexConnex could continue to increase 10 percent per year as applications of computer technology extended into industrial products and consumer products such as automobiles and appliances.

PLANNING MEETING
At a meeting of his staff, Tom Richards, director of manufacturing planning, stated that they needed to plan to bring additional capacity for FlexConnex online in about two years. He suggested that they begin by proposing possible alternatives. The staff quickly identified three promising alternatives:

1. The Santa Clara plant had been designed for future expansion. Additional space was available at the site, and new production capacity could be easily integrated into the existing production processes as long as compatible manufacturing technologies were employed.

2. CTI owned a plant in Waltham, Massachusetts that manufactured a product line that was being phased out. Some existing equipment in the Waltham plant was compatible with the Santa Clara plant's manufacturing technology and could be converted to the production of FlexConnex. Half of the Waltham plant would be available in 2003, and the remainder in 2005.

3. CTI could build a greenfield plant in Ireland, close to its major European customers. To attract such industries, the Irish government would make a site available at low cost. A new technology currently being Beta-tested by an equipment manufacturer could be used to equip this plant.

Tom believed that these three were promising proposals. To ensure CTI could bring additional, profitable, FlexConnex capacity online in two years, Tom felt that they should begin developing plans for these alternatives. Nonetheless, he wanted the staff to keep an open mind to additional alternatives even as they evaluated these three. As the discussion started to wind down, Gracie Stanton, an engineer, said that she had a suggestion.

Gracie: Before we spend our time developing these three alternatives in detail, I'd like to get a rough feel for the potential profitability of each alternative. We shouldn't waste our time developing detailed plans for an alternative if there is no chance it will ever show a positive NPV.

Tom: Good point, Gracie. Let's break up into three groups, and do back-of-the-envelope calculations based on what we currently know about each alternative. Gracie, would you head up the Santa Clara group, since you were part of the engineering team for that plant? Edward Lodge, how about Waltham? Ian Townsley, could you and your folks take a look at Ireland? To start, what are the facts and assumptions about each facility?

Gracie: Well, there's enough space at the Santa Clara site to produce an additional 30 million units annually. I expect it would cost about $23 million to expand this plant, and bring its total capacity to 105 million units. Of the $23 million, we would spend $5 million to expand the building, and $18 million for additional equipment compatible with Santa Clara's existing manufacturing process. All $23 million would probably be spent in 2003, and the plant would be ready for production in 2004.

I assume that the selling price per unit will remain at its current level; further, since the same manufacturing technology will continue to be used, the variable manufacturing cost will remain the same as we show on the 2002 Santa Clara Cost Analysis Sheet [Exhibit 1]. Expanding the existing plant would allow some fixed manufacturing costs, like the plant manager's salary, to be shared with the existing facility, so I estimate that the additional fixed manufacturing costs, excluding depreciation, will be $2.1 million annually beginning in 2004. In 2006, these fixed costs will rise to $2.4 million and remain at that level for the foreseeable future.

Edward: Well, the Waltham plant is smaller than the space available in Santa Clara, so I think its capacity will be about 25 million units. It will require renovations to adapt the plant to manufacture FlexConnex, say, about $2 million, and approximately $12 million for equipment. Half of this would be spent in 2003, and half in 2005. Initial production would begin in 2004; half of the 25-million-unit capacity should be available in 2004; two-thirds in 2005; the remainder in 2006.

Since the Waltham plant will use the same technology as Santa Clara, we can assume that the variable manufacturing costs will be the same as Santa Clara's. Selling prices will also be the same. However, since Waltham will be a stand-alone faculty, its fixed manufacturing costs, excluding depreciation, would be somewhat higher: $2.4 million annually beginning in 2004. In 2006, however, fixed costs will increase to $2.6 million annually, where I expect them to remain for the foreseeable future.

Ian: I just visited the Beta-test site for the manufacturing equipment using the new technology that I propose we use for the Greenfield plant. There I learned that the economic size for a plant using this technology to manufacture a product such as FlexConnex is about 70 million units, so I propose that we prepare our estimates for Ireland based on a 70-million-unit capacity plant. Of course, this will cost more, since it is much larger than other sites. With the help of the Irish government, an appropriate site can be obtained for about $1 million. A building large enough to produce 70 million units can probably be built for about $10 million, and equipping the facility with the new technology equipment will cost about $50 million. Most of this would be spent in 2003, although as much as 10 percent might be spent before the end of 2002 to acquire and prepare the site. The plant would begin production in 2004; some areas of the plant would not be complete, however, and as much as 20-25 percent of the investment would remain to be spent during 2004.

Although FlexConnex's worldwide selling price will be the same as for the other facilities, the new equipment will lower the variable manufacturing cost to $0.195 per unit. The efficiency of this new plant will help keep fixed manufacturing costs down, as well, but since the facility will be so large, fixed manufacturing costs, excluding depreciation, would be higher than the other two facilities: $2.8 million annually beginning in 2004, rising to $2.9 million annually beginning in 2008.

Tom: These assumptions sound like reasonable first cuts to me. Let's just start with a five-year analysis, 2003 through 2007, using the discount rate of 20 percent, which the corporate finance manual states is the hurdle rate for capital investments. For simplicity, let's assume all cash flows occur at the end of the respective year. Discount everything to today's dollars, that is, as of the end of 2002. And, consistent with corporate policy, we'll do a pretax analysis; we'll ask the corporate finance staff to evaluate the tax implications later.
A few minutes later, the buzzing of the small groups died down, and the tapping on the laptop keyboards had ceased.

Tom: Well, what have you learned from this first glance?

Edward: The Waltham site looks promising.

Ian: Not Ireland.

Gracie: This is odd. The Santa Clara plant is right on the margin, and that surprises me since the existing manufacturing facility is one of CTI's most profitable, and we get further economies of scale by expanding that plant. I wonder if the discount rate we are using is too high. At the "Finance for Manufacturing Engineers" seminar I attended recently, we discussed the problems associated with using a discount rate that was too high. The professor stated that there was a sound theoretical basis for using a discount rate that approximated the company's cost of capital, but many companies "added on" estimates for risk, corporate charges, and other factors that were less well grounded. Based on what I learned in that seminar, I tried to estimate CTI's actual cost of capital; it was about 10 percent. I wonder what would happen if we used 10 percent instead?

Tom: With these laptops and spreadsheet programs, that's easy enough; let's check it out.

A few seconds later . . . .

Gracie: Now, that's better!

Edward: Ours too.

Ian: Well, at least we're moving in the right direction. But it doesn't make sense to me that a facility with lower variable cost per unit, and lower average fixed cost per unit at capacity, shows a negative NPV when the others are positive. We checked our calculations; what's the story? Could it be that Ireland would not even be up to capacity production in five years because the plant is so big?

Gracie: Maybe, but our plants are being penalized, too; after all, even though they reach capacity in the first five years, they will presumably continue to produce FlexConnex. Although there is constant technological change in this industry, there is a reasonable probability that demand for FlexConnex will remain strong for at least 10 years.

Ian: Well, then, let's look at each of the three plants over a ten-year period, using Gracie's 10 percent discount rate.

Later . . . .

Edward: Aha! Waltham continues to improve.

Gracie: However, Santa Clara has you beat now!

Ian: I've got bad news for both of you!

QUESTIONS:
1. Prepare the manufacturing staff's calculations for the three alternatives:
a. In the first set of calculations, the staff used a discount rate of 20 percent, a five-year time horizon, and ignored taxes and terminal value. What is the relative attractiveness of these three alternatives?
b. In the second set, they used a 10 percent discount rate. What happens to the NPV of each alternative? What happens to their relative attractiveness? Why?

------------------------------------

EXHIBIT 1 FlexConnex Cost Analysis Sheet
Santa Clara Plant, 2002

Plant Capacity: 75 million units

Selling Price/Unit: $0.85

Variable Cost/Unit: $0.255

Fixed Manufacturing Cost: $9.5 million annually (includes $2.5 million depreciation)

Estimated Plant Profitability at Capacity:

Revenue $63,750,000

Variable Cost <19,125,000>

Fixed Manufacturing Cost <9,500,000>

Plant Profitability a $35,125,000

a Excludes interest expenses and corporate selling, general and administrative expenses.

Attachments
Purchase this Solution

Solution Summary

This solution just does the five year forecast to get the student started. It includes calculating the three alternatives for question 1 a and 1 b only.

Solution Preview

This should give you "the idea" and you can adjust it, extend it the ten ...

Solution provided by:
Education
  • BSc, University of Virginia
  • MSc, University of Virginia
  • PhD, Georgia State University
Recent Feedback
  • "hey just wanted to know if you used 0% for the risk free rate and if you didn't if you could adjust it please and thank you "
  • "Thank, this is more clear to me now."
  • "Awesome job! "
  • "ty"
  • "Great Analysis, thank you so much"
Purchase this Solution


Free BrainMass Quizzes
Paradigms and Frameworks of Management Research

This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.

Social Media: Pinterest

This quiz introduces basic concepts of Pinterest social media

Income Streams

In our ever changing world, developing secondary income streams is becoming more important. This quiz provides a brief overview of income sources.

Learning Lean

This quiz will help you understand the basic concepts of Lean.

MS Word 2010-Tricky Features

These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.