Using the following project information (Times are estimates in weeks):
Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) Variance Expected Time
A 3 6 9 none 1.000 6.00
B 3 5 7 A 0.444 5.00
C 4 7 12 A 1.778 7.33
D 4 8 10 B 1.000 7.67
E 5 10 16 C 3.361 10.17
F 3 4 5 D,E 0.111 4.00
G 3 6 8 D,E 0.694 5.83
H 5 6 10 F 0.694 6.33
I 5 8 11 G 1.000 8.00
J 3 3 3 H,I 0.000 3.00
The critical path is A-C-E-G-I-J.
(a) Calculate the probability that the project will be completed in 38 weeks.
(b) Calculate the probability that the project will be completed in 42 weeks.
Purchase this Solution
Solution Summary
Solution describes the steps to calculate the desired probability values in the given case.
Solution Preview
The properly formatted solution is attached.
(a) Calculate the probability that the project will be completed in 38 weeks.
Expected time to complete the project (A-C-E-G-I-J )=sum of expected times of activities on critical path
=6.00+7.33+10.17+5.83+8.00+3.00
...
Education
- BEng (Hons) , Birla Institute of Technology and Science, India
- MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
- "Thank you"
- "Really great step by step solution"
- "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
- "Thanks Again! This is totally a great service!"
- "Thank you so much for your help!"
Purchase this Solution
Free BrainMass Quizzes
Measures of Central Tendency
This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.
Terms and Definitions for Statistics
This quiz covers basic terms and definitions of statistics.
Measures of Central Tendency
Tests knowledge of the three main measures of central tendency, including some simple calculation questions.
Know Your Statistical Concepts
Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.