If a company took 100 hours to assemble their first unit and 85 hours to assemble the second unit, we might expect it to take:
70 hours to assemble the third unit.
72.25 hours to assemble the fourth unit.
72.25 hours to assemble the third unit.
70 hours to assemble the fourth unit.

Purchase this Solution

Solution Summary

The solution gives complete solutions for applying the exponential distribution. All formula and calculations are shown and explained.

Solution Preview

Since this is obviously a linear relation, we guess it as an exponential ...

Purchase this Solution


Free BrainMass Quizzes
Know Your Statistical Concepts

Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.

Measures of Central Tendency

This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.

Terms and Definitions for Statistics

This quiz covers basic terms and definitions of statistics.

Measures of Central Tendency

Tests knowledge of the three main measures of central tendency, including some simple calculation questions.