structure and solve a linear programming problem using Excel
Not what you're looking for?
AC's take 3 hours of wiring and 2 hours of drilling. Fans take 2 hours of wiring and 1 hour of drilling. 240 hours of wiring and 140 hours of drilling are available during production cycle. Each AC sold yields $25 profit and each fan yields $15 profit.At least 20 ACs should be made and no more than 80 fans should be made. What is the optimal solution?
Purchase this Solution
Solution Summary
Shows how to structure and solve a linear programming problem using Excel solver add-in.
Solution Preview
See the attached file for complete solution. The text here may not be copied exactly as some of the symbols / tables may not print. Thanks
Let quantiy ...
Purchase this Solution
Free BrainMass Quizzes
Terms and Definitions for Statistics
This quiz covers basic terms and definitions of statistics.
Measures of Central Tendency
This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.
Know Your Statistical Concepts
Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.
Measures of Central Tendency
Tests knowledge of the three main measures of central tendency, including some simple calculation questions.