4. Southern Valley Mills' Richmond plant has four machine operators to be assigned to four machines. The time in minutes required by each worker to produce 100 pounds of carpet on each machine is shown in the following table:

Machine (Min.)
Operator A B C D
1 10 12 9 11
2 5 10 7 8
3 12 14 13 11
4 8 15 11 9

Determine the optimal assignment and compute total minimum time.

Purchase this Solution

Solution Summary

This posting contains solution to following assignment problem.

Purchase this Solution


Free BrainMass Quizzes
Measures of Central Tendency

Tests knowledge of the three main measures of central tendency, including some simple calculation questions.

Terms and Definitions for Statistics

This quiz covers basic terms and definitions of statistics.

Know Your Statistical Concepts

Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.

Measures of Central Tendency

This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.