    The Fix-It Shop has added a fourth repairman, Davis. Solve the accompanying cost table for the new optimal assignment of workers to projects.

    PROJECT

    Worker 1 2 3

    Adams $11 $14 $6
    Brown 8 10 11
    Cooper 9 12 7
    Davis 10 13 8

    A. Is this a balanced or unbalanced problem?
    B. What special circumstance step will have to be added to solve this problem?
    C. To what project will the new employee, Davis, be assigned?
    D. In this problem, you have 3 projects and 4 repairmen. If you were going to fire a repairman based solely on his/her cost to the company and this project, which repairman would you fire? Explain

    © BrainMass Inc. brainmass.com June 3, 2020, 9:01 pm ad1c9bdddf
    https://brainmass.com/statistics/descriptive-statistics/fix-it-shop-162818

    Solution Summary

    The expert solves the accompanying cost table for the new optimal assignment of workers to projects.

    $2.19

    ADVERTISEMENT