    An analyst has timed a metal cutting operation for 50 cycles. The average time per cycle was 10.40 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 125 percent. Assume an allowance of 16 percent of job time. Find the standard time for this operation.

    © BrainMass Inc. brainmass.com March 4, 2021, 9:21 pm ad1c9bdddf
    https://brainmass.com/economics/economic-systems/237320

    Solution Preview

    Hi,

    Please see response to your posting as follows.

    For calculating standard time, we need average observed ...

    Solution Summary

    Solution shows calculations of standard time for th the given job