I have to track the following activites here at work for a project to be scheduled using CPM.

Activity Immediate Predecessor Time (Week)

A none 6
B A 3
C A 7
D C 2
E B, D 4
F D 3
G E, F 7

A. Draw the Network
B What is the critical path?
C. How many weeks will it take to complete the project?
D. How much slack does activity B have?

Purchase this Solution

Solution Summary

Excel file contains Network digram and calculations of critical path and expected time.

Purchase this Solution


Free BrainMass Quizzes
Lean your Process

This quiz will help you understand the basic concepts of Lean.

Business Processes

This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.

Six Sigma for Process Improvement

A high level understanding of Six Sigma and what it is all about. This just gives you a glimpse of Six Sigma which entails more in-depth knowledge of processes and techniques.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.