For that mixture what is the lowest ratio mixed model assembly sequence?

I cannot get this to work? 200 MC per day (100 KZ440, 60 KZ650, 40 KZ1000) /3 = 33.333 and 20, and 13.333 = 66.666

In September 1981, a Japanese management team replaces the American plant manager at the Kawasaki motorcycle plant in Lincoln, Nebraska. One goal of the new managers was to convert the main motorcycle assembly line to mixed model production. The line had been running production lots of at least 200 of each model between line changeovers.

The conversion was expected to take about three months. It required two kinds of
exacting preparation:

1. Identification: All parts, tools, cartons, racks, and so forth, had to he clearly labeled so that an assembler would be able instantaneously to identify and select the right one. With a different motorcycle model next on the conveyor, delay in identifying it and all of the parts and tools to go with it would be intolerable. A color-coding system was devised so that, for example, all items related to a KZ6SO motorcycle would he labeled with a gummed red dot. Even the position of the colored dot on the carton, part, or tool had to be precisely designed.

2. Placement. Engineers, material controllers, foremen, and assemblers all pitched in to devise exact locations for all parts and tools at work stations along the assembly line. The assembler, on seeing what the next model of motorcycle is, should be able to reach for the correct parts and tools blindfolded. Better racks, containers, and holding fixtures were designed to feed parts and hold tools in the right positions.

The preparations (which today we would refer to as preautomation) were successful. On January 1, 1983, the main assembly line fully converted to mixed-model production.

At that time, the production volume was at about 200 motorcycles per day. That 200 might consist of the following models: 101) KZ44Os, 60 KZ65Os, and 40 KZ1000s.

Purchase this Solution

Solution Summary

This posting contains one problem on lowest ratio mixed assembly planning.

Solution Preview

For lowest ratio mixed model:
The greatest common denominator of 100, 60 and 40 is 20.
Therefore, the KZ440:KZ650:KZ1000 = ...

Purchase this Solution


Free BrainMass Quizzes
Employee Orientation

Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.

Organizational Leadership Quiz

This quiz prepares a person to do well when it comes to studying organizational leadership in their studies.

Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.

Writing Business Plans

This quiz will test your understanding of how to write good business plans, the usual components of a good plan, purposes, terms, and writing style tips.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.