Forecasting Techniques: Exponential Smoothing

This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

YEAR 1 2 3 4 5 6 7 8 9 10 11
DEMAND 7 9 5 9 13 8 12 13 9 11 7

Develop a forecast for year 2 through 12 using exponential smoothing with α = .4 and a forecast for year 1 of 6. Plot your new forecast on a graph with the actual data and the native forecast. Based on a visual inspection, which forecast is better?

© BrainMass Inc. brainmass.com March 22, 2019, 3:07 am ad1c9bdddf
https://brainmass.com/business/operations-research/601668

Solution Summary

This solution depicts the steps to generate a forecast by the exponential smoothing method.