Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows:

YEAR PROJECT A PROJECT B
1 $ 5,000,000 $20,000,000
2 10,000,000 10,000,000
3 20,000,000 6,000,000

What are the two projects' net present values, assuming the cost of capital is:
a) 10%?
b) 5%?
c) 15%?

Purchase this Solution

Solution Summary

Excel file attached finds the NPV of 2 projects for various cost of capital values.

Purchase this Solution


Free BrainMass Quizzes
Marketing Management Philosophies Quiz

A test on how well a student understands the basic assumptions of marketers on buyers that will form a basis of their marketing strategies.

Accounting: Statement of Cash flows

This quiz tests your knowledge of the components of the statements of cash flows and the methods used to determine cash flows.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

SWOT

This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.

Motivation

This tests some key elements of major motivation theories.