Labor price variance & Total quantity variance

Not what you're looking for?

Ask Custom Question

Company X has set their standard labor rate at $25 per hour and a particular job has a standard time of 2.5 hours to complete. The company accountant is looking over last months results for this job, and, the accountant sees that the actual labor rate was $32 per hour and the time to complete each job was 1.8 hours. The company produced 100,000 units. What is the total labor price variance for this job? The accountants computes the total quantity variance as:

Purchase this Solution

Solution Summary

The solution computes the labor price variance and the total quantity variance.

Solution Preview

Standard Labor rate = 25
Actual Labor rate = 32
Standard time = 2.5 hrs
Actual Time = 1.8 hrs
Units = 100,000
Actual Hours = ...

Purchase this Solution


Free BrainMass Quizzes
Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

Academic Reading and Writing: Critical Thinking

Importance of Critical Thinking

Team Development Strategies

This quiz will assess your knowledge of team-building processes, learning styles, and leadership methods. Team development is essential to creating and maintaining high performing teams.

Motivation

This tests some key elements of major motivation theories.

Introduction to Finance

This quiz test introductory finance topics.