Question 23
Olson Corporation constructs new homes. Assume that Olson uses a job costing system. During May 2010, the following transactions occurred:

Olson purchased $4,500 of lumber on account.
Olson used $3,750 of lumber in production and incurred 50 hours of direct labor hours at $15 per hour.
Depreciation of $1,500 on equipment used to build new houses was recorded.
A house that was completed last period at a cost of $150,000 was sold for $180,000 in cash.

The journal entry to record the requisition of lumber for Olson would include a
debit to Work-in-Process of $4,500.
debit to Materials Inventory of $3,750.
credit to Finished Goods of $3,750.
debit to Work-in-Process of $3,750.

Question 36
The Kraig Corporation manufactures custom-made purses. The following data pertains to Job XY5:

Direct materials placed into production $4,000
Direct labor hours worked 50 hours
Direct labor rate per hour $ 15
Machine hours worked 100 hours

Factory overhead is applied using a plant-wide rate based on direct labor hours. Factory overhead was budgeted at $60,000 for the year and the direct labor hours were estimated to be 15,000. Job XY5 consists of 50 units.

What the total cost assigned to Job XY5?
a- $5,150
b- $4,400
c- $4,200
d- $4,950

Purchase this Solution

Solution Summary

Olson Corporation constructs new homes. Assume that Olson uses a job costing system. During May 2010, the following transactions occurred:

Olson purchased $4,500 of lumber on account.
Olson used $3,750 of lumber in production and incurred 50 hours of direct labor hours at $15 per hour.
Depreciation of $1,500 on equipment used to build new houses was recorded.
A house that was completed last period at a cost of $150,000 was sold for $180,000 in cash.

The journal entry to record the requisition of lumber for Olson would include a
debit to Work-in-Process of $4,500.
debit to Materials Inventory of $3,750.
credit to Finished Goods of $3,750.
debit to Work-in-Process of $3,750.

The Kraig Corporation manufactures custom-made purses. The following data pertains to Job XY5:

Direct materials placed into production $4,000
Direct labor hours worked 50 hours
Direct labor rate per hour $ 15
Machine hours worked 100 hours

Factory overhead is applied using a plant-wide rate based on direct labor hours. Factory overhead was budgeted at $60,000 for the year and the direct labor hours were estimated to be 15,000. Job XY5 consists of 50 units.

What the total cost assigned to Job XY5?
a- $5,150
b- $4,400
c- $4,200
d- $4,950

Solution Preview

Question 23: When the lumber was bought, Olson debited Materials Inventory for $4,500 and credited accounts payable for the same amount. When it transferred the $3,750 to the job, it debited Work-In-Process for $3,750 and credited Materials ...

Purchase this Solution


Free BrainMass Quizzes
Learning Lean

This quiz will help you understand the basic concepts of Lean.

Business Ethics Awareness Strategy

This quiz is designed to assess your current ability for determining the characteristics of ethical behavior. It is essential that leaders, managers, and employees are able to distinguish between positive and negative ethical behavior. The quicker you assess a person's ethical tendency, the awareness empowers you to develop a strategy on how to interact with them.

Lean your Process

This quiz will help you understand the basic concepts of Lean.

Marketing Research and Forecasting

The following quiz will assess your ability to identify steps in the marketing research process. Understanding this information will provide fundamental knowledge related to marketing research.

Organizational Leadership Quiz

This quiz prepares a person to do well when it comes to studying organizational leadership in their studies.