Final Contract price of a CPIF Contract

This content was STOLEN from BrainMass.com - View the original, and get the already-completed solution here!

Given the following information regarding a CPIF contract, what would be the final contract price at the different final cost amounts.

Target Cost $2,000,000
Target Fee $ 150,000

Share Ratio:

Under Target 90/10
Over Target 80/20
Maximum Fee $ 240,000
Minimum Fee $ 60,000

a. Final cost is $1,000,000
b. Final Cost is $1,800,000
c. Final cost is $2,150,000
d. Final cost is $2,400,000

© BrainMass Inc. brainmass.com October 25, 2018, 9:34 am ad1c9bdddf
https://brainmass.com/business/finance/578890

Solution Summary

Given the following information regarding a CPIF contract, what would be the final contract price at the different final cost amounts.

$2.19
See Also This Related BrainMass Solution

Cost Plus Incentive Fee Contract

1. Given the following data, develop an appropriate CPIF pricing arrangement.

Cost Fee
Target $100 $10
Optimistic $ 80 $12
Pessimistic $120 $ 7

a. What should be the maximum fee?

b. What should be the minimum fee

c. What should be the under-target share ratio?

d. What should be the over-target share ratio?

e. What is the range of incentive effectiveness?

2. Given the following data for CPIF pricing arrangement

Target Cost $200
Target Fee $ 16

Share Ratios:

Under target 80/20
Over target 85/15
Maximum Fee $ 26
Minimum Fee $ 10

What is the range of incentive effectiveness?

3. Given the following information regarding a CPIF contract, what would be the final contract price at the different final cost amounts.

Target Cost $2,000,000
Target Fee $ 150,000

Share Ratio:

Under Target 90/10
Over Target 80/20
Maximum Fee $ 240,000
Minimum Fee $ 60,000

a. Final cost is $1,000,000

b. Final Cost is $1,800,000

c. Final cost is $2,150,000

d. Final cost is $2,400,000

View Full Posting Details