South California Furniture Inc. produces all types of office furniture...

Please see ** ATTACHED ** file(s) for complete details!!

South California Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks:

task performance time task must follow
(min) task listed below
A 4 --
B 7 --
C 6 A, B
D 5 C
E 6 D
F 7 E
G 8 E
H 6 F, G

a- Draw a precedence diagram of this operation.
b- What is the cycle time for this operation?
c- What is the theoretical minimum number of workstations?
d- Assign tasks to workstations.
e- How much total idle time is present each day?
f- What is the overall efficiency of the assembly line?

Can you provide algebraic details for all calculations?

Attachments

Solution Preview

See the attached file. Thanks

South California Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks:

task performance time task must follow
(min) task ...

Solution Summary

The expert examines task performance time and the theoretical minimum number of workstations.