Kanban usage of products

Not what you're looking for?

Ask Custom Question

Weekly Usage of a product is 8 units. The plant operates 50 weeks per year, this lead to an annual usage of 400 units. The setup cost is $40 and annualized carrying cost is $80. Weekly production of this product is 12 units. Lead time is 4 weeks and Safety Stock is 1 week's production.

What is the optimal Kanban size?
What is the optimal number of Kanbans?

Purchase this Solution

Solution Summary

The optimal size and numbers of Kanban produced each week is determined.

Purchase this Solution


Free BrainMass Quizzes
Operations Management

This quiz tests a student's knowledge about Operations Management

Team Development Strategies

This quiz will assess your knowledge of team-building processes, learning styles, and leadership methods. Team development is essential to creating and maintaining high performing teams.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

Basics of corporate finance

These questions will test you on your knowledge of finance.

Introduction to Finance

This quiz test introductory finance topics.