Weekly Usage of a product is 8 units. The plant operates 50 weeks per year, this lead to an annual usage of 400 units. The setup cost is $40 and annualized carrying cost is $80. Weekly production of this product is 12 units. Lead time is 4 weeks and Safety Stock is 1 week's production.
What is the optimal Kanban size?
What is the optimal number of Kanbans?
Purchase this Solution
Solution Summary
The optimal size and numbers of Kanban produced each week is determined.
Purchase this Solution
Free BrainMass Quizzes
Operations Management
This quiz tests a student's knowledge about Operations Management
Team Development Strategies
This quiz will assess your knowledge of team-building processes, learning styles, and leadership methods. Team development is essential to creating and maintaining high performing teams.
Balance Sheet
The Fundamental Classified Balance Sheet. What to know to make it easy.
Basics of corporate finance
These questions will test you on your knowledge of finance.
Introduction to Finance
This quiz test introductory finance topics.