National Cranberry Cooperative:
1. Develop a process flow diagram for processing cranberries (both wet and dry). Show the capacities at the different stages.

2. What are the sources of variability affecting NCC's operations?

3. Suppose that a peak harvest-season day involves 18,000 barrels of berries, 70% of them wet harvested, arriving uniformnly over a twelve-hour period from 7 a.m. to 7 p.m. Would trucks have to wait to unload? When during the day would trucks be waiting? How much truck waiting time would you expect? What is the maximum number of trucks waiting during the day?

4. If it costs $20 per hour to rent a truck and driver, how much money is spent by truck waiting on a peak day?

5. Is the investment in a light meter system a good option?

Purchase this Solution

Solution Summary

The solution is attached as a 1200+ word document to allow for the flow diagram's formatting.

Solution Preview

Hello

Please find guidelines and ideas for National Cranberry Cooperative in the attached file.

Running Head: NATIONAL CRANBERRY COOPERATIVE

National Cranberry Cooperative

Answer 1
Process Flow Diagram for wet and dry cranberries

Working Note:
Arrival of berries- In the process fruit, first berries are arrived on receiving plant no.1. In which, average truck delivery was 75bbls.
Capacity of Temporary Holdings- 27 bins are used for holding both dry and wet berries. In which, 1-24 holding bins will hold 250bbls of barriers each and 25-27 will held 400 bbls of berries each.
Total capacity is: [(250*24) + (400*3)]
[6000 + 1200] that is 7200 bbls.
Destoning capacity- There are 3 destoning units and capacity of each unit is 1500 bbls, so the total capacity of destoning unit is: (1500 * 3) that is 4500 bbls.
Dechaffing capacity- There are 3 dechaffing units and capacity of each unit is 1500 bbls, so the total capacity of dechaffing unit is: (1500 * 3) that is 4500 bbls per hour.
Drying Capacity- There are 3 drying units and capacity of each unit is 200 bbls, so the total capacity of drying unit is: (200 * 3) that is 600 bbls.
Milling Capacity- In this step, berries are transferred to separator building from receiving building. Two types of quality grader are used in this step first jumbo separators and other is bailey mills. For this, 3 separator units are used, in which average capacity of each unit is 400 then total capacities are 1200 bbls (400 *3).
Bulking Capacity- Berries are directly loaded into bulk trucks. There are 2 bulk stations and capacity of each station is 1000 bbls, ...

Purchase this Solution


Free BrainMass Quizzes
Introduction to Finance

This quiz test introductory finance topics.

Marketing Research and Forecasting

The following quiz will assess your ability to identify steps in the marketing research process. Understanding this information will provide fundamental knowledge related to marketing research.

Production and cost theory

Understanding production and cost phenomena will permit firms to make wise decisions concerning output volume.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

Situational Leadership

This quiz will help you better understand Situational Leadership and its theories.