    Basic Estimating Problem

    Your company is installing a new piece of machining equipment and a robotic arm. Your manager asks for the project costs by cost category as well as the total amount. Given the following information, develop a base cost estimate by grouping costs by Equipment / Material (items 1 - 4), Installation / Labor (items 5 and 6), and Overhead (items 7-9).

    1. Two pieces of equipment costing $ 15,000 and $ 35,000
    2. Material required for electrical hook-up is 400 feet at $ 25 per foot
    3. Controls for each piece of equipment are estimated at $ 600 each
    4. Required start-up material is 3,700 pounds at $ 2.70 per pound
    5. Company labor for installation requires two maintenance specialists for two days at eight hours per day and $ 35 per hour
    6. Contract labor is estimated at a fixed price of $ 7,500
    7. Engineering is estimated to be 15% of (equipment / material) cost based on past experience
    8. Inspection is estimated to be 3% of (labor) cost based on past experience
    9. General and Administrative expenses are estimated to be 5% of the total of (equipment / material) and (labor) based on past experience.

    Note: For this problem, only items 5 and 6 are considered "labor" for the purpose of calculating items 8 and 9.

    Check answer: Total project cost = $94,737.60

    © BrainMass Inc. brainmass.com October 10, 2019, 2:14 am ad1c9bdddf
    https://brainmass.com/business/business-management/basic-estimating-problem-368831

    Solution Summary

    This solution provides assistance with the problem regarding basic estimating.

    $2.19