    Nova Company's total overhead costs at various levels of activity are presented below:

    Month Machine Hours Total Overhead Costs
    April 70,000 $198,000
    May 60,000 $174,000
    June 80,000 $222,000
    July 90,000 $246,000

    Assume that the total overhead costs above consist of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 60,000 machine-hour level of activity is:

    Utilites (variable) $48,000
    Supervisory salaries (fixed) 21,000
    Maintenance (mixed) 105,000
    Total overhead costs $174,000

    Required:

    1. estimate how much of the $246,000 of overhead cost in July was maintenance cost
    2. Using the high-low method, estimate a cost formula for maintenance
    3. Express the company's total overhead costs in the linear equation form Y = a + bX
    4. What total overhead costs would you expect to be incurred at an operating level of 75,000 machine hours?

    © BrainMass Inc. brainmass.com October 10, 2019, 2:42 am ad1c9bdddf
    https://brainmass.com/business/accounting/nova-company-high-low-method-389988

    Solution Preview

    1. The total overhead cost has three components - utilities, supervisory salaries and maintenance. We need to subtract utilities and supervisory salaries to get the maintenance cost.
    Utilities is a variable cost which implies it would be fixed on per unit and vary in total. We are given that utility cost is 48,000 at 60,000 machine hours. Calculate the ...