    Gigabyte, Inc. manufactures 3 products for the computer industry:
    -(product G): annual sales, 8,000 units
    -(product T): annual sales, 15,000 units
    -(product W): annual sales, 4,000 units
    The company uses a traditional, volume-based product-costing system with manufacturing overhead applied on the basis of direct-labor dollars. The product costs have been computed as follows:

    Product G Product T Product W
    Raw Mat...............$35.00............................$52.50...............................$17.50
    Direct Labor..........16.00(.8hr.@$20).............12.00(.6hr.@$20)...............8.00(.4hr.@$20)
    Manuf. Overhead...140.00.............................105.00..............................70.00
    Tot. Prod. Cost......$191.00...........................$169.50.............................$95.50

    Manuf.Overhead Budget:
    Machine setup..........$ 5,250
    Machinery..................1,225,000
    Inspection....................525,000
    Material Handling..........875,000
    Engineering..................344,750
    Total..........................2,975,000

    Direct Labor Budget(based on budgeted annual sales)
    Product G: 8,000x$16.00= $128,000
    Product T: 15,000x$12.00= 180,000
    Product W: 4,000x$8.00= 32,000
    Total...........................................$340,000

    pred overhead rate=budgeted overhead/budgeted direct labor=875%

    Gigabyte's pricing method has been to set a target price equal to 150% of full product cost. However, only product T have been seelling at the target price. The target and actual current prices for all three products are the following

    Product G Product T Product W
    Product cost.....................$191.00..............$169.50.............$95.50
    Target Price.......................286.50................254.25.............143.25
    Actual Current selling Price.213.00.................254.25.............200.00

    Gigabyte has been forced to lower the prices of product G in order to get orders. In contrast, Gigabyte has raised the price of product W several times, but there has been no apparent loss of sales. Gigabyte, Inc. has been under increasing pressure to reduce the price even further on product G. In contrast, Gigabyte's competitor do not seem to be interested in the market for product W. Gigabyte apparently has this market to itself.

    Gigagbytes controller, nan 0'second recently attended a conference at which activity-based costing systems were discussed. In stage one of the ABC project, each cost driver was identified for each activity cost pool. Finnally, the ABC project team compiled data showing the percentage of each cost driver that was consumed by each of Gigabyte's product lines.
    These data are summarized as follows:
    Activity Cost Pool Cost Driver Product G ProductT Product W
    Machine setup number of setups 20% 30% 50%
    Machinery machine hrs 25% 50% 25%
    Inspection number of inspections 15% 45% 40%
    Material Handling raw-material costs 25% 69% 6%
    Engineering number of change orders 35% 10% 55%

    --Is product G the company's least profitable product?

    --Is product W a profitable product for Gigabyte, inc.?

    --what are the competitors reactions in regards to gigabyte's pricing strategy?

    --What dangers does gigabyte inc. face?

    **develop product costs for the tree products on the basis of an activity-based costing system(round to nearest tenth)

    **calculate a target price for each product, using gigabyte's pricing formula. Compare new target prices with the current actual selling prices and previously reported product costs.

    --construct an excel spreadsheet to solve the above 2(**) show how the solution will change if the inspection activity was divided among the three product in the following manner: product G 20%;product T 40%, and product W, 40%

    © BrainMass Inc. brainmass.com June 3, 2020, 8:44 pm ad1c9bdddf
    https://brainmass.com/business/accounting/important-information-about-traditional-costing-vs-activity-based-costing-150284

    Solution Summary

    The solution explains the calculations under traditional costing and activity based costing